Fairfax Keeps New Data Centers 200 Feet From Homes. It Just Approved 1,042 Homes 100 Feet From One.

On 17 November, Fairfax County approved up to 1,042 homes on the Lake Fairfax Business Center site in Reston. The nearest will sit about 100 feet from a data center that was already there. Here is how the county got to yes, and the conditions it set.

The rule

Since September 2024, Fairfax County's Zoning Ordinance has kept new data centers at least 200 feet from homes (amendment ZO 112.1-2024-9, adopted 10 September 2024, section 4102.6.A(4)). A lesser distance needs a special exception.

The rule governs data centers built near homes. Lake Fairfax runs the other way: homes built beside a data center that is already there.

The site

The Lake Fairfax Business Center is about 49 acres of offices in Reston, half a mile from the Metro. Under the rezoning brought by EYA, all seven office buildings come down and homes take their place. Next door, outside the rezoned site, a three-story data center stays.

Supervisor Walter Alcorn (Hunter Mill) described the case at the board's 17 November meeting: "This is a redevelopment of much of an old office park that has become vacant. And the office uses are no longer viable."

How close

At the Planning Commission's hearing on 23 September, Commissioner Evelyn Spain (Sully) raised the distance directly: "The elephant in the room, you're close to a data center now… The new development is 100 feet away from the residences."

Our own reading of the applicant's plan sheet (CDP sheet C-09E) is consistent with that: roughly 80 to 110 feet from the nearest new homes to the data center, an approximate measurement.

The commission asked for evidence

Commissioner Spain set the concern against the county's own standard: "All the concerns that neighbors have, that even the 200 feet is still uncomfortable for them."

Commission chair Phillip Niedzielski-Eichner put the test plainly: "It's a matter of practical pragmatism on our part and not burdening a future generation of homeowners with something that we could have avoided or fixed prior to building homes."

That night the commission deferred its decision, 9–0 (Planning Commission action, 28 September).

What the study found

The applicant answered with a low-frequency noise analysis by its acoustic consultant, Phoenix Noise & Vibration, dated 1 October and passed to the commission in a county staff memo on 9 October.

In the audible low-frequency range (20 to 100 Hz), the study measured 55 dB or less from the data center. That is lower than the traffic it measured on the Dulles Toll Road (at 78 feet), Sunset Hills Road (125 feet) and Sunrise Valley Drive (30 feet).

The consultant also noted how the building differs from today's data centers: no outdoor generators, no chillers, and six cooling towers on the side facing away from the new homes.

A different site, a different sound

Neighbors elsewhere have raised noise too. In Prince William County, beside a newer and larger campus at Great Oak in Manassas, Dale Browne spoke for his homeowners' association at the Board of County Supervisors on 10 June 2025: "This is just kicking the can down the road. And I have to ask, do you have the courage to do what's right for the residents of Prince William County, or is this industry money too important to you?"

Great Oak is a different site, beside a newer and larger campus, and is shown here for context only.

The conditions

The approval carries Proffer 23, noise attenuation for uses near the data center (executed proffers, 16 November 2026):

  • Before the first residential building permit in that part of the site, the developer must submit a refined acoustic study of homes proposed within 200 feet of the data center's exterior wall, for county review and approval.

  • Homes expected to see outdoor noise above 65 dBA Ldn must be built to bring it down to no more than 45 dBA Ldn inside and 65 dBA Ldn outside.

  • Where rooftop areas are expected to exceed 65 dBA Ldn, that must be disclosed in the HOA documents and sales materials.

  • A solid fence at least six feet high screens the data center from the homes, subject to the necessary easements.

The decision

Three weeks after the deferral, with the study in hand, the Planning Commission recommended approval on 14 October, with one abstention. On 17 November the Board of Supervisors approved the rezoning 10–0. EYA plans to start construction from late 2027, as reported by FFXnow.

The case took two commission hearings. The applicant came back with measurements rather than assurances, and the commission and board gave the noise question the time it needed.

What it means for applicants

For builders and land-use attorneys working near existing infrastructure, three points follow.

First, the 200-foot rule runs one way. It sets how close a new data center may come to homes. Homes proposed beside an existing one are weighed in the rezoning itself, as here.

Second, the record mattered. The commission deferred on an open question and recommended approval once a measured answer was on file.

Third, the conditions are the precedent. A refined noise study within 200 feet, interior and exterior noise limits, disclosure to buyers and screening are now on the record for the next application like this one. Precedent, not prediction.

About 100 feet is Commissioner Spain's figure on the record; UNDA's reading of the plans gives roughly 80 to 110 feet and is approximate. Noise figures are from the applicant's consultant study as filed with the county.

About UNDA Development
UNDA Development provides planning and permit intelligence for builders, land-use attorneys and planners: every application, every board decision, every condition at your fingertips. Our sister product, UNDA Management, provides strata market intelligence for NSW strata managers. Learn more at unda.technology

Previous
Previous

Loudoun Pauses Its Data Center Votes. More Than $1.3 Billion of Building Carries On.

Next
Next

One Bondi Junction Building, Three Consents. $17.5 Million Declared to Council, $120.8 Million in the Developer's Own Cost Report.