Loudoun Pauses Its Data Center Votes. More Than $1.3 Billion of Building Carries On.

On 17 November, Loudoun County's Board of Supervisors adopted a pause on data center and substation cases that need its vote. Data centers paid the county $1.2 billion in property tax last year. Here is what the pause holds, and what carries on regardless.

From the White House

Three days after the vote, the White House posted a clip in which President Donald Trump said: "There's one area right next to Loudoun County where they have a lot of data centers. They're making so much money, they don't know what to do with it."

What data centers pay

In fiscal 2026, data centers paid Loudoun County $1.2 billion in real and personal property tax: 39% of the county budget, or almost 40 cents of every dollar. The adopted budget projects about $1.3 billion, or 40%, for fiscal 2027.

What the board adopted

On 17 November the Board of Supervisors voted 7–1, with one abstention, to pause new data center cases that need its approval. Supervisor Kristen Umstattd voted against and Supervisor Kershner abstained.

Each case will wait up to a year while the county writes new rules: up to 12 months per application, in effect since 15 September. The pause covers data center and substation applications that need a board vote, not by-right projects or existing data centers. Substations needed for grid reliability can still be heard, and zoning conversions in the Route 28 tax district are left out.

In the pipeline

The county's staff report counted 33 active applications when it was written: ten data centers, twelve substations, ten that combine both, and one for grid reliability. It is a delay, not a refusal.

At least nine of them are likely to reach their 12-month deadline before the new rules are ready. Staff will ask those applicants to wait until at least September 2027.

What carries on

Projects that do not need a vote carry on. On building permits still open with the county (snapshot of 29 October 2026), more than 20 new data center buildings declare more than $1.3 billion of construction.

That figure is deliberately narrow. Only building permits for new data center construction are counted. Zoning and trade permits for the same project repeat the same declared value, so they are left out, as are fit-outs, shells and permits with no declared value. Two permits carry an identical value and floor area and may be one building counted twice; counting them once gives $1.36 billion, and counting both gives $1.44 billion.

What is planned

More are planned. On 6 November, Virginia Business reported that Amazon had bought 23 acres near Dulles Airport for a data center 100 feet tall, on land zoned for 45 feet. Amazon plans to seek two special exceptions from the board, one for the use and one for the height: the kind of vote the pause now covers. It has not yet filed, and its timing depends on the Planning Commission.

On the record

The people who spoke were split.

  • Supervisor Juli Briskman (Algonkian): residents feel data centers and their energy infrastructure are "encroaching on their quality of life and even their health." (Bisnow, 4 August 2026)

  • Supervisor Kristen Umstattd (Leesburg), who voted against the pause: "There will be tremendous school costs that we are not going to be able to pay for without a growing data center cohort in Loudoun County." (Bisnow, 4 August 2026)

At the 15 September public hearing, as reported by Loudoun Now:

  • Bryan Turner, general counsel, Lansdowne Conservancy: "A limited pause will not stop every additional substation or data center, but it will send a clearer signal…"

  • Don Slaiman, political coordinator, IBEW Local 26: "The consequences are immediate for working people."

  • Clement Lupton IV, government relations manager, Loudoun Chamber of Commerce: a pause "freezes the county's activity without resolving any of these underlying questions."

For residents, a trade

For residents, data center tax helps pay for schools and services. Neighbors have also raised noise, and new high-voltage lines.

In February 2025 the State Corporation Commission approved Dominion Energy's Aspen–Golden transmission line along Route 7 (case PUR-2024-00032), rejecting the county's push to bury it. The Supreme Court of Virginia upheld the approval on 19 February 2026. Dominion expects the line in service by June 2028, as reported by Loudoun Now.

What it means for applicants

For builders and land-use attorneys with a Loudoun project, three points follow.

First, the path decides the timeline. A data center or substation that needs a board vote now waits for the new rules. A by-right project, or one already permitted, does not.

Second, the deadline does not end the wait. Where an application reaches its legal deadline first, staff will ask the applicant to wait until at least September 2027.

Third, the rules come before the decisions. Applications decided after the pause will be measured against standards that are not yet written. The decisions made before it are the precedent for that system, not a prediction of it.

Permit figures are declared values on Loudoun County open building permits, snapshot 29 October 2026; UNDA analysis, lower bound. The Amazon purchase is as reported by Virginia Business.

About UNDA Development
UNDA Development provides planning and permit intelligence for builders, land-use attorneys and planners: every application, every board decision, every condition at your fingertips. Our sister product, UNDA Management, provides strata market intelligence for NSW strata managers. Learn more at unda.technology

Next
Next

Fairfax Keeps New Data Centers 200 Feet From Homes. It Just Approved 1,042 Homes 100 Feet From One.